Category Archives: Danville Rte. 2 Updates

Danville Rte. 2 Update – Week Oct. 3, 2011

DANVILLE RTE. 2 CONSTRUCTION NIGHT WORK Water line and drainage installation will continue on Route 2 from Highland Drive towards the school Sunday night through Thursday night. Crews will also be working on Route 2 near the school installing new … Continue reading

Posted in Danville Rte. 2 Updates | 691 Comments

Danville Rte. 2 Updates – Blasting Information

BLASTING NOTICE – WEEK OF 9/26/11 BLASTING:  Crews will begin blasting on Tuesday, September 27, 2011 along Route 2 near Walden Hill Road and the Danville School.  Blasting in this area is expected to last from Tuesday through the end of … Continue reading

Posted in Danville Rte. 2 Updates | 532 Comments

Danville Rte. 2 Project – Traffic Alert

TRAFFIC ALERT FOR PARK STREET Crews will close access to Park Street from Route 2 today, Wednesday, Sept. 21st and Thursday, Sept. 22nd during daytime work hours to continue drilling ledge.  Motorists are encouraged to use Peacham Road, when coming … Continue reading

Posted in Danville Rte. 2 Updates | Comments Off

Danville Rte. 2 Construction – Sept. 9 Alert

TRAFFIC ALERT FOR PEACHAM ROAD Crews will close Peacham Road from the Post Office to Route 2 Friday, September 9th, 2011 to connect the existing main water line to the new main water line. This closure is expected to last … Continue reading

Posted in Danville Rte. 2 Updates | 712 Comments

Danville Rte. 2 Construction – Sept. 7, 2011 Traffic Alert

TRAFFIC ALERT – HIGHLAND AVE Crews will close access to Highland Ave at the intersection of Route 2 today to relocate sewer lines.  This closure is expected to last from 8 am to 3 pm.  The contractor will make every … Continue reading

Posted in Danville Rte. 2 Updates | 753 Comments

Danville Rte. 2 Construction – Week of Sept. 5, 2011

Work Update Danville Route 2 Project  Pike Industries will continue work on the Danville Route 2 project as follows: For the month of September, crews will extend their work week to include Saturdays. Saturday work hours are tentatively set for … Continue reading

Posted in Danville Rte. 2 Updates | Comments Off

Danville Rte. 2 Construction – Hurricane Irene Update

TRAFFIC ALERT 8/25/11 With the expected arrival of Hurricane Irene over the weekend, crews will be working on completing some drainage work in an effort to avoid the flooding issues on the project that were experienced during the May storms. … Continue reading

Posted in Danville Rte. 2 Updates | 663 Comments

Danville Rte. 2 Construction – Week of Aug. 22, 2011

Pike Industries will continue work on the Danville Route 2 project as follows: – Crews will continue to work on Route 2 between Marty’s and the Village Green installing storm drain.  Motorists can expect alternating one-way traffic within this construction … Continue reading

Posted in Danville Rte. 2 Updates | Comments Off

Rte. 2 Construction – Hill Street (8/16/11)

TRAFFIC ALERT 8/16/11 – Hill Street and Danville Green Previously, crews had planned to work on Hill Street for two days; today, Tuesday, 8/16/11 and tomorrow, Wednesday, 8/17/11.  In an effort to restore parking tomorrow for Diamond Hill Store and … Continue reading

Posted in Chamber Made Column, Danville Rte. 2 Updates | 401 Comments

Danville Rte. 2 Construction-Revised Aug. 15, 2011 week

REVISED Work Update Danville Route 2 Project Project: Pike Industries will continue work on the Danville Route 2 project as follows: 8/15/11 – Due to unfavorable weather conditions today, crews have postponed the work on the corner of Route 2 … Continue reading

Posted in Danville Rte. 2 Updates | 407 Comments